2021 Pavement Mill and Overlay Project

Village Hall Web

Village of Whitefish Bay 2021 Pavement Mill and Overlay Project

Henry Clay Street:  Santa Monica Boulevard to Marlborough Drive

Oakland Avenue:  Hampton Road to Glendale Avenue

The Village of Whitefish Bay Public Works Department is under contract with Stark Pavement Corporation to complete Village pavement milling and repaving improvements.  The project will involve the grinding off 2 inches of asphalt or concrete pavement and then repaving with new asphalt pavement.  Pavement marking will then be applied the week following the paving work. 

This work is scheduled to begin the week of May 3, 2021, weather permitting, with completion scheduled by mid May 2021, again weather dependent.  There will be no assessment to any property owner for this work.   Access to your property will be maintained throughout the project.  Only while work is taking place directly in front of your driveway would your access be restricted or limited. The Village would ask that you refrain from parking your vehicles within the project limits on both Henry Clay Street and Oakland Avenue during this construction period.   Regarding vehicle parking, the Whitefish Bay Police Department have been made aware of this project and on street parking concerns. 

Work hours for this project creating noise are limited to 7:00am - 5:00pm Monday through Saturday.  The Public Works Department staff understands the inconvenience that this project may create for you and greatly appreciates your patience and understanding.  Please be careful, slow down and pay extra attention when driving around this and all construction zones. 

If you should have any questions regarding this project, feel free to contact:


Spencer Charczuk, E.I.T.

Village of Whitefish Bay Staff Engineer

(414) 962-6690 ext. 123